The cover article of the brand new issue of Moscow Defense Brief (subscription required) from the Center for Analysis of Strategies and Technologies, examines developments in Russian military shipbuilding in 2012, written by Dmitry Boltenkov. Since the article is not publicly available, I thought it might be useful to provide a brief summary. Part 1 covers submarines and surface ships. Part 2, coming soon, will cover auxiliary ships, export contracts, and provide some analysis.
Submarines
Construction of Borei-class (project 955) submarines progressed significantly in 2012. The navy took delivery of the Yury Dolgoruky, the first sub of this class, at the end of 2012. After some training exercises, the sub is expected to enter regular service by the end of 2013. The second sub, the Alexander Nevsky, is expected to be commissioned in the fall. The third sub, whose construction started in 2006, was launched in January 2013, while construction of the fourth started in July 2012. Two more subs are to be laid down this year. Given the 7-8 year construction times on these submarines, it seems unlikely that all eight will be completed by the 2020 target date. 2023 seems to be a more realistic goal. Furthermore, the lack of new tests on the Bulava missile in 2012 is concerning, though additional tests are expected this autumn — most likely using a new automated missile launch control system.
The Yasen-class (project 885) nuclear attack submarines are being built far more slowly, with the first submarine in the class (the Severodvinsk, which was laid down back in 1993) currently undergoing tests and expected to enter the fleet later this year. The Kazan (the second submarine of this class) will be commissioned in 2015 at the earliest, with the third to be laid down in July. Again, the chances of all 8 contracted subs being completed by 2020 is virtually nonexistent.
Diesel submarines are also being built, including the recently restarted, but still troubled, Lada class. The first sub in this class, the St. Petersburg, entered sea trials in 2004. Problems with its propulsion systems have prevented its commissioning and led the project to be suspended indefinitely several years ago. The project was restarted in 2012, but the St. Petersburg still has not been commissioned. Construction on the two other subs in this class that were laid down before the suspension has resumed and they are expected to be ready for sea trials in 2015 and 2016, respectively. MDB reports that the second boat may be equipped with new lithium-ion batteries, while the third may have air-independent propulsion. It seems unlikely that any more subs of this class will be built, which means the navy will get three essentially different boats, each with its own maintenance needs. This is precisely the sort of the thing the Russian military has been trying to get away from. The hope is that a fifth-generation conventional sub currently being designed by Rubin Design Bureau will soon be ready for construction, obviating the need for the Lada class. In the meantime, the navy will have to depend on old and new Kilo-class submarines. The first of a set of six improved Kilos is expected to be launched later this year. Two more are under construction and another is to be laid down by the end of 2013. All six are expected to be in service by 2016.
Surface ships
The first of the two Mistral-class ships ordered from France is currently under construction, with the second to be laid down sometime in 2013. Both ships are to be completed and delivered to Russia by the end of 2015. Boltenkov reiterates that both will be assigned to the the Pacific Fleet. Furthermore, he notes that the Russian Navy has ordered four assault-landing boats from STX L’Orient in France. The fate of the third and fourth Mistral-class ships, which were to be built entirely in Russia starting in 2016, remains unresolved.
Two types of frigates are being built for the navy. The first of the Admiral Gorshkov class (project 22350) frigates is expected to enter sea trials in late 2013. Two others are under construction, with a fourth to be laid down later this year. Two more ships of this class have been ordered, with hopes of completion by 2020. MDB reports that the project is facing serious delays with its primary Poliment-Redut SAM weapon system, which is being developed by Almaz-Antey (a company that has had many problems successfully completing the development of new weapons systems in recent years). The second type of frigate (project 11356R) is essentially the Talwar class previously built for the Indian Navy. This is an updated version of the Soviet Krivak class. Russian defense industry is much better at building updated versions of tried and tested designs than at building something completely new. It’s therefore not surprising that construction on these ships is proceeding quite quickly, with three ships already under construction and another to be laid down this year. The first ship of this class, the Admiral Grigorovich is expected to be launched this summer and to enter service in 2014.
The navy is also receiving some smaller combat ships. Construction on various versions of the Steregushchiy class (projects 20380 and 20385) of corvettes continues, with two in service, one in sea trials, one expected to begin sea trials later this year, three under construction and another to be laid down in July. Severnaya Verf is building these ships in about three years, while Amur shipyard is taking much longer. Various sources indicate that contracts have been signed to build another 10 of these corvettes, which would bring the total number in service to 18 by the time the program is complete.
Several types of ships are being built expressly for the Caspian Flotilla. The Dagestan missile ship, equipped with Kalibr-NK long-range cruise missiles, was commissioned into the Caspian Flotilla in November 2012. No further ships of this type are planned, however. Two Buyan-class (project 21630) small artillery ships were commissioned into the flotilla in 2012. An updated version of this class (project 21631), to be armed with Kalibr-NK cruise missiles, has been ordered. Five ships are now under construction with an estimated completion date of 2015. A contract for three more of these ships was signed in January 2013. The Caspian Flotilla is also expected to receive three Serna class (project 11770) high speed air-cavity landing craft this year, built according to an existing late Soviet design.
Finally, the navy is building a number of specialized surface ships, including the Admiral Gren (project 11711) large tank landing ship, which has been under construction since 2004 and was finally launched in May 2012. Completion will be no earlier than 2014 and initial plans to build another 4-5 of these ships have been shelved. Four Dyugon class (project 21820) high speed amphibious landing craft are also under construction, though Boltenkov reports that problems with the design mean that no more ships of this type will be built once these four are completed. The first ship of the Aleksandrit class of minesweepers (project 12700) is under construction as well, with three more expected to be built in the near future. Two Grachonok class (project 21980) anti-sabotage boats were commissioned in 2012, with two more expected to be completed by the end of 2013 and another four currently under construction. A total of about 20 are expected to built in the next few years.
Dmitry Gorenburg is a Senior Analyst at CNA blogging for PONARS Eurasia on military and security affairs in Russia and Eurasia. This comment is also available on Russian Military Reform.